RAWSON URD PROJECT

URD Cable was installed from each existing transformer to the next in preparation for transformer replacement.  Once all of the new cable was installed, the new transformers were staged at the job and installed.  The process of transformer change-out necessitated a short power outage for those customers serviced by the transformer being replaced.  A total of 47 transformers were affected by this job.

The job designations in the following schedule refer to the cable between two transformers and the specific phase of the line that the transformer will be powered from.  For example, line 5 below refers to the installation of Phase C cabling from transformer #12 to transformer #13.

Cable installation will be accomplished using both directional boring equipment and trenching equipment.