Schedule
Transformers

RAWSON URD PROJECT

THIS PROJECT IS CLOSED!

This project upgraded the URD (Underground Residential Distribution) electrical system in the Rawson area.  This project is being completed by PIEPERLINE, under contract with WE Energy.  This project started on January 6, 2000 and completed on March 6, 2000.  Restoration for this job completed on June 30, 2000.